Surface preparation

Chipping and removing the existing loose materials. Grinding the surface with mechanical grinder and clean the surface.


Product locking grooves

Cutting anchoring grooves perimeter with walls and columns if any from all sides. Grooves must have a depth and width of twice the thickness of the flooring thickness.


Scratch-coat application

Providing and application of one coat primer ( Solvent base / Water base as per site condition) over the prepared surface.


Flooring

Providing and laying of PU self-leveling flooring (Solvent base / Water base as per site condition and specified thickness ) over the prepared surface in specific colour.


Yellow marking

Yellow marking with polyurethane paint over the self-leveling flooring for Gang ways and Machine area separations.